Thursday, August 16, 2007

Rest Place inside each WING

The rest place inside each WING was modified. In all 3 WINGs, permanent Tables and Chair are being build. Shafi's idea. He says plants willbe planted later at the corners.






Before













After.. incomplete.

Partition between Block A and the Rumah Papans


The old broken wire mesh wall between Block A and the rumah papans in front beside Jln Hj Mokhtar, is replaced with 5 feet high Metel Decks.

Partition Wall between Block A and Block B

The partition wall between Block A and Block B is in progress. A 8 feet high metal deck is being installed.





Sahfi insist on fixing a door to Block B for the indons and kampung pasir people who illegally occupy and cultivate some fish pond there.

A rumah papan had been turn into a Rela Post.










Another view..
















Again top view.. show the partition wall. This wall is temporary. The news is that when Block B is developed the wall must come down.

Drainage Cover

Most of the drainage are exposed. Sahfi want the drainage to be covered with concreate covers. So, the construction of the concrete covers is in progress..






Exposed drainage. Example of exposed drainage. Its everywhere.














Concrete covers with steel mesh inside is being mold.















Molding in process..










Same here.. more concrete cover being mold.

MotorBike Parking Shade

Presently we hv one temporary motorbike parking area below Wing3 near the Bilik Air and Bilik TNB. The area is insufficient as there are more Motorbikes than the shade can offer. Some tenents keep parking their motorbikes in the walkways to the Lift even when there is enough space at the parking area. Some tenents are just plain inconsiderate to others. We have decide to build a motorbike area near the entrace to estana court. The area takes about 8 car park place. Pic below.

Once complete, all motorbike must be parked under the shade provided. MC/security will lock any bikes parked in other areas.






top view
















another view.















ground level view.. still under construction.

Entrance View to Estana Court

Entrace to Estana Court. Some paint job been done.








Estana Court Logo at the entrace.
Wall painted.














Guard House was also painted.
Lever-Gate installed.

Tuesday, August 07, 2007

Telephone cable

As we all know, around the year 2005/6, some bloody animal had cut and stolen the telephone cables in the telephone riser rooms to all floor.

Last week the works for re-installing telephone cables to all floor had began.






installation of new telephone cable is in progress.








Works in telephone riser room at ground floor.

Paint Work

For the past 4 days, since 2August07, paint works at ground floor is in progress. Sahfi had decide to do two tone paint work at ground floor, but only ground floor will be painted. Walls, cable conduits and doors will be painted.

For the wall, a darker and lighter orange color was selected by him.





Note the newly installed notice boards. One for PPPEC and the other for MC-MIHRAB









First coat being painted..

Making passage/road between block A and B

The swampy area between Block A and Block B is cleared and filled with gravels. Soon this will make way for a access road to fire hydrant and rubbish/refuse collection room at WING-1.





Backhoe clearing the swampy land and filling with earth.










Gravel/rock/earth were filled and level..











Crusher-run were filled and leveled.









another view..

Lanscape

To the suprise of many, our Big Taiko had desided to cut trees which was part of the landscape, created by the defunct developer in accordance with MJAP requirement. Five big trees were cut, remaining 3 small trees. Sahfi says he got some plans for the area, he wants to plant some plants and make some sort of sitting shade. We shall see...






Gone








Gone


Clearing Drainage

According to Shafi, MPAJ had given verbal warning to clean up the drainage around estana court.

On the 10July07 backhoe was hired to clean-up the drainage.
















backhoe in action...



Lighting at main entrance




Before installing light at the entrace to estana court.. estana court logo not so visible.








After installing light at the logo.










Before installing light at the main entrace











street lights changed to brighter lights.

Monday, August 06, 2007

Installing elbow joints

Will post more pictures of revival works.



Last July07, new drainage elbow-joint was installed. Developer promista did not installed all the drainage pipes properly, some were missing. The missing elbow joins for the drainage at the corridoor-way was replaced with new ones.







missing elbow joint.









fixing of new elbow