Electrical Works 6 -TNB seal

Electricity deposite of RM10000 was already paid about 2 months back at Melawati TNB branch.

Re-energizing the TNB supply is taking time as there are 3 separate departments from 3 different area are involve. Electrician Abu is doing the communication with all the 3 branches to re-energize electricity to the MSB room.
1. TNB Melawati: For account registration and meter.
2. TNB Kepong : For meter panel, meter and fuse seal checking.
3. TNB Selayang: For energizing meter electric supply.

The meter panel have to be sealed with TNB seal to prevent tempering. A penalty will be charged if any broken seal was detected by TNB people after the electric was activated and meter start working. So the seal was important to be in place first before electric is energized.

On 3/10/06, the TNB guys from Kepong branch came and checked and sealed the meter panel.
Now we are waiting for the TNB guys from Selayang to come and energize the electric meter. Our electric contractor, Abu is communicating with the TNB guys.







Kepong TNB guy are checking the meter panel.













Kepong TNB guys sealing the fuse, meter and the panel.