Thursday, August 31, 2006

Night View 30/08/06

Some night time pictures taken on merdeka eve.



With most of the common area lights repaired and powered by Gen-Set. A thanksgiving prayer was conducted by Hj.Basiron in a temporary surau as suggested by Sahfi.







The street light is also switched on.











Most of the AJK members and some buyer who saw the lighted up estana court also turn up for the gathering.

Wednesday, August 30, 2006

Electrical Works 2 - Common Area Lighting 2

The streetlights and the landscape lights were being set-up for the past few days. Took few photo shots of the Abu and his man working to fix the lights.


The lighting at the landscape were in bad condition. Wires damaged, broken and short circuiting. Abu and his man laying out the cable under the ground and covering back the cables.





Abu fixing the newly installed cables to the lamp post.







Abu and his man fixing the light bulbs and the glass covers.
30/08/06 3.30pm

Thanks to Sahfi for sponsoring to rectify the damaged landscape cables, lights and the glass cover.

Tuesday, August 29, 2006

Water Works6 -29/08/06

Inspection of internal piping by Syabas officers.

The inspection was the result of PPPEC asking Syabas to the waive of consultant acknowledgment and stamp for the "as build drawing". Old consultant appointed by promistar developers are no longer interested as they did not receive payment from promista. Hiring new consultant fee is very high, estimated cost would be more than RM20000. The process for this consultant issue been going on for months. Already, PPPEC had send letters and document to Syabas requesting the Syabas to waive the consultant acknowlegdment.

Tn Hj Yusof bin Saroji, pengurus besar syabas gombak, came to estana court at 4.30pm on 29/08/06 and witness the piping condition at estana court. Finally he agreed to waive consultant acknowledgment plus the stamping, provided Tukang Paip confirms the piping is in good condition and another letter from PPPEC to Syabas stating that MC and PPPEC would take responsibilities for the piping.



Syabas general manager Tn Hj Yusof and syabas officer En Halim, their driver together with Tukang Paip Zarkhan making a surprise visit to estana court to check the internal piping to the water tanks.




Inspection at the "Bilik Tangki Air" at the ground floor. Tukang Paip, Zarkhan explaining to the Tn Hj Yusof and En Halim.






More questions from Syabas being answered by Zarkhan and Sahfi.






End of inspection. Syabas gombak MG and his officers were satisfied with the explaination given by Tukang Paip about the piping layout.
Seen here, syabas officers En Halim and Tn Hj Yusof waiting for the rain subside before going back to syabas gombak.

Water Works 5 - 28/08/06

The water tank in the BILIK AIR in the ground floor was checked and serviced. Missing water overflow pipe was installed. The missing incoming water pipe to the water tank was installed. Water pump checked and confirmed in working condition.


A portion of the pipe to the water tank in the "Bilik Tangki Air" was missing. Tukang paip replaced the missing pipe.






The water pumps in the "Bilik Pump Air" was tested and confirmed working. The power supply was temporarily modified so that it can b operated from the power supplied from Gen-Set.





The picture shows the water pumped up from the tank in the Bilik Tangki Air" from the ground floor is poring into the tank at the roof top.






The water level sensor in the roof top tank. Need to be serviced.

Saturday, August 26, 2006

Electrical Works 1 - Common Area Lighting 1

Our electician, Abu have started repairing the corridor florescent lights. The electrical power supply for testing the florescent lights are supplied by the Gen-Set. The Gen-Set uses diesel. So the Gen-Set will not be in operation all the time. Till the TNB supply is connected, the Gen-Set will be used intermittently.



Abu checking all the lights from floor to floor. Of cause Abu was not alone, he had 2 more electricians to asist him. Forget to snap their photos. next time.





The building common corridor lighting from ground floor up to 7th floor was rectified. Spoiled florescent bulb and starters were replaced. The rest of the corridor light will be serviced on monday(29/08/06).

Friday, August 25, 2006

Lift Bomba is OK

Today the lift bomba is serviced and is in operational state. Test run of the Lift Bomba was carried out today with electric supply generated by the Gen-Set.


Lift repair man Abbas confirming the Lift control panel is in good condition.

Report is aspected from him.








The Lift CPU in operating state.








Abbas with the help of our securityman Ramli, fixing the control switches taken from passenger lift. Many switches were missing/stolen.

Information from Ramli is that he(Ramli) had witnessed Ariffin removing those switches some months back.



Abu replacing the damaged florescent lights. All the light in the Bomba lift was spoiled.








Testing the Lift. In picture left to right:Abbas, Abu, Sahfi and Ramli.

Abbas wants some sort of barrier on the floor to stop waters entering the lift.

Thursday, August 24, 2006

Lift Bomba

With fund running thin, AJK had decided to service and repair only one lift. The other 2 lift will be repaired when the more fund is available. The least damaged lift was the lift bomba. Lift service man from Dover maintenance Service Sdn Bhd, En Ismail was hired to repair and make the lift bomba in operation. The work will take few days.

Temporary electric supply for the bomba lift will be supplied by the gen-set. The gen-set is serviced and is in running condition. The electrical cable to the bomba lift which was stolen was also replaced.

1) Electrical chargeman En.Abu checking and rectifying the electrical cables to the bomba lift in the MSB room.







2) Seen here, Abu checking the cables connections at the roof top Bomba Lift room.







3) The cables to the Bomba Lift at the roof top electrical switch board is restored. Power is supplied from the gen-set is checked. 3phase supply is confirmed to be at 415Volt.






4) Bomba Lift motor at roof top.








5) The picture shows the central control system panel. The control system was intact, no vandalism on the system. If it was stolen then it would have been very costly.






6) Lift maintenance people, En Ismail and En Abbas setting-up the bomba lift control panel. Seen here Abbas checking the control cards.

Wednesday, August 23, 2006

Roof top water tank.

Next stage in the water issue is to check for any water leakage in the water tanks and internal piping. To do this we need water from syabas to fill up the 5 water tanks in the roof top. 3 tanks for consumer/domistic use and 2 tanks for bomba water tanks. Payments for the water was already made last month.

Based on the water tank measurement, the water quantity of 388.6m3 at the rate of 1.92 per m3 for the sum of RM746.11 was paid to syabas on the 4/7/06. This water will be pumped up to the roof top tank then leakage testing will be done.

To pump up the water, electricity is needed to supply current to the water pump motor. Generator(gen-set) in the Gen-Set room will be serviced and it will provide the electric to the water pump motor. Servicing of the get-set is in progress.

Hot tapping will be done by Tukang paip with Syabas's knowlendge. This involves the main pipe at the main road. I guess a portion of the road from the main road will be excavated.



This is the generator set in the gen-set room. A very high powered generator. This gen-set is being serviced and will be set up soon.







Another view of the gen-set.

Holes covered up and sealed with tarmac

The holes created by the Backhoe when seacrhing for the leaking hydrant pipe was covered. The surface was sealed with tarmac by Tukang Paip.



1)Naughty boys from kampung, trying to turn the holes dug by the Tukang Paip into mini swimming pool.












2)The mini swimming pool is covered. Too bad the boys have to find another place to play.












3)The trench dug to lay the hydrant paip for hydrant #2 is sealed with tarmac.












4) The hole at hydrant #2 is also sealed with tarmac. Orther smalls holes dug by the Tukang paip was sealed.

Tuesday, August 15, 2006

Area between Block A and Block B

A "before and after" picture of the area between Block A and Block B where the Hydrant#3 is located.

This area in future need to be leveled and tarmaced so that fireengine can pass thru to access the fire hydrant. This area also need to be separated with fence/wall from Block B.



28 May 2006 . The path between Block A and Block B is messy and dangerous.












10August 2006. The path between Block A and Block B is cleared for Hydrant work. Looks much better without the broken fence, scrubs and bushes.

Saturday, August 12, 2006

Water Works4 - 10/08/06

External Piping Inspection by Syabas officer along with Tukang Paip.



(21) - End of inspection. Syabas officer Anuar is satisfied with the piping pressure check. In the picture from left: Sahfi(representing PPPEC), Tukang Paip Zarkhan with his man Sajee and Syabas officer Anuar.











(20) - Syabas officer checks the pressure gauge as the water is released from the consumers pipe.












(19) - Syabas officer inspecting the water pressure gauge on the comsumer and hydrant pipe (estana court side) at the guard house.












(18) - Tukang Paip showing the water pressure from the incoming pipe which split into consumer and fire hydrant outlet.












(17) - Tukang Paip explaining to Syabas officer. Watched by Sahfi.












(16) - Syabas officer, Anuar(yellow shirt) from Syabas Bandar Baru Selayang, Gombak, with Tukang Paip( Zarkhan) and Sahfi(white shirt) at Estana Court entrance where the water pressure check is done.

Water Works3 - 07/08/06

Final Hydrant pipe pressure check before Syabas officer is called for inspection.




(15) - Hydrant pressure test at hydrant#1 with all 3 Hydrant connected together. Hydrant#2 is new along with its piping. Hydrant pressure test show 15psi. Pressure Test pass.











(14) - Tukang Paip worker fixing hydrant pressure gauge at hydrant #1













(13) - Tukang Paip workers draining water from the hole before works on the damaged Hydrant valve and the Hydrant is done.












(12) - Leaking hydrant (hydrant #3). Shows water quirting from the crack.

Water Works2 - 02/08/06

Search for the cause of hydrant pressure failure.



(11) - Found Pipe connecting Block A with Block B. The pipe connecting to Block B will be isolated by endcap.











(10) - Excavating land seaching for Pipe connecting Block A with Block B.












(9) - Tukang Paip man at work in rain.













(8) - Tukang Paip giving instruction to his workers.












(7) - Pressure check for hydrant piping from meter inlet to hydrant#1. Pressure gauge shows full pressure 250psi.











(6) - “Tukang Paip” workers pumping water into hydrant pipe and checking the water pressure in the hydrant pipe. Pressure test fails as water is leaking somewhere in the hydrant piping.