Abu fixing the newly installed cables to the lamp post.
Abu and his man fixing the light bulbs and the glass covers.
30/08/06 3.30pm
Thanks to Sahfi for sponsoring to rectify the damaged landscape cables, lights and the glass cover.
"CONDOMINIUM"
The old Promista Office at Ground Floor had been turn into a Surau. Loud Speakers been installed by MC to please some people and irritate some people.
* More Revival works started since Aug07. The payment for new works come from Stakeholder Fund. Works done include the following
i).. fencing work between Block A and Block B... (DONE)
ii).. fencing work between Block A and Rumah Papans .. (DONE)
iii).. telephone cable ...(UNKNOWN STATUS)
iv).. paint works .. .(DONE - STOPPED)
v).. MotorBike Parking Shade.. (DONE - but still not enough).. update : 3 car park slots were converted into motorbike parking area without shade.
vi).. Drainage Cover.. (DONE).
vii).. landscape improvement .. in progress.
viii).. Childrend Playground.. (DONE).
ix).. Lift Bomba ok
x).. Even Floor Lift .. (DONE) ( Down again since last year)
Repair done by new management.
xi).. Odd FloorsLift ..(DONE)
xii).. Installing Fire Extinguisher. (DONE.. only at ground floor)
Installed back at all flour with breakglass box by new management.
xiii).. Repairing Bomba Tank and Hose reel Pipes. ( STATUS UNKNOWN.. actually work was not done at all).
xiv).. Water Tank.. 4 more roof top tanks waiting for repair. ( STATUS UNKNOWN.. not done at all)
xv).. Doors common area riser room doors ( DONE )
xvi).. Individual Letter Boxes been installed.. (DONE but not maintained, many boxed been damaged)